Draft Project Schedule

If the bond issue is approved by Wyoming voters, a draft project schedule would be planned as follows.

January-December 2025: Hilltop Design Phase

January 2026-June 2027:

  • Elm School and Vermont School design phase

  • Hilltop School construction - Hilltop students in temporary school at WHS

August 2027: New Hilltop School opens

July 2027-December 2028:

  • Vermont School Construction - Vermont students in temporary school at WHS

  • Elm School Construction - Elm students in temporary school at WMS

January 2029: New Elm and Vermont Schools open

Wyoming Primary Schools timeline.png

Timeline presented in Wyoming Primary Facilities Master Plan